Regulatory Library · USDA
7 CFR 4280 Subpart B: REAP Grants
7 CFR 4280 subpart B governs Rural Energy for America Program (REAP) grants for renewable energy systems and energy efficiency improvements, and since October 16, 2026 a renewable energy applicant can file a Resource Assessment or a Feasibility Study. Feasibility Study Company prepares the independent feasibility studies the subpart describes. The grant itself cannot pay for one. This page quotes the sections that decide it 12.
Subpart B now covers renewable energy systems and efficiency grants only.
The rewrite moved energy audit and development assistance grants into their own subpart.
Subpart B governs REAP grants for renewable energy systems (RES) and energy efficiency improvements (EEI) 1. The same rule created subpart C for energy audit and renewable energy development assistance grants, effective October 16, 2026 3. A feasibility study done under the development assistance program is a different thing from the study an RES applicant submits under subpart B, and subpart C defines it separately: renewable energy development assistance covers “conducting a Renewable Energy Site Assessment, Resource Assessment, and Feasibility Studies” 3.
For the guaranteed loan side of REAP, the rule is 7 CFR part 5001, covered on our part 5001 page. For how a study is scoped in practice, see our REAP feasibility study page.
Deadlines stay on the USDA deadline calendar.
Section 4280.104 defines the study and its preparer.
The preparer is an independent professional, and the study is tied to a specific site.
Section 4280.104 defines a feasibility study as “a report, conducted by an independent professional possessing relevant knowledge, expertise, and experience, that includes an opinion or finding evaluating the economic, market, technical, financial, and management feasibility of a proposed Project or operation located at a specific site in terms of its expectation for success” 1. USDA's preamble says the definition was revised to clarify that the individual conducting the report must have relevant knowledge, expertise and experience, and that the findings must relate to the proposed project at a specific site 2.
Two practical points follow. A study of a technology in general does not meet the definition, because it must address the applicant's site. And the preparer must be independent of the project: the preamble to 4280.106 treats it as a conflict of interest if the RES developer conducts the Feasibility Study, although that statement appears only in the preamble and not in the codified text 2.
Four sections decide whether a study is submitted, what it holds and who pays.
Each rule is quoted from the section that states it.
Choice. Section 4280.122(a)(8) addresses technical sustainability for RES projects: “RES Projects must demonstrate this information through a Resource Assessment or a Feasibility Study, as described in paragraphs (a)(8)(i) and (ii) of this section” 1. The application section repeats it. Under 4280.131(b)(3), “For RES Projects, the Applicant must provide a Resource Assessment, or the Applicant can provide a Feasibility Study in lieu of a Resource Assessment” 1. EEI projects follow a different route, an Energy Assessment or an Energy Audit 1.
Content. Section 4280.122(a)(8)(ii) says a Feasibility Study “must include the following content,” listed in the table below 1.
Cost. Section 4280.125(b)(7) names “Feasibility studies” in its list of unallowable uses of funds 1. The applicant pays for the study outside the grant. A Resource Assessment is allowable under 4280.125(a)(4) unless the cost was charged to another federal award 1.
| Paragraph | Component | What the text lists |
|---|---|---|
| 4280.122(a)(8)(ii)(A) | Economic analysis | “a cost-benefit analysis,” with inputs, contracts, environmental risks, cost relative to revenue or benefits, and overall economic impact 1 |
| 4280.122(a)(8)(ii)(B) | Market analysis | Current and future market potential, competition, sales or service estimates, buyers and End Users; six listed items from competition to industry risk 1 |
| 4280.122(a)(8)(ii)(C) | Technical analysis | Reliability of the technology and delivery of goods or services; nine listed items from commercial availability to construction risk 1 |
| 4280.122(a)(8)(ii)(D) | Financial analysis | Ability “to achieve sufficient income, credit, and cashflow to financially sustain the Project over the long term and meet all debt obligations”; twelve listed items including source of repayment and sensitivity analysis 1 |
| 4280.122(a)(8)(ii)(E) | Management analysis | Legal structure, ownership, governance and management; history, background, experience, skills and qualifications 1 |
| 4280.122(a)(8)(ii)(F) | Recommendation | “The recommendation of the independent professional(s) conducting the Feasibility Study must be included” 1 |
| 4280.122(a)(8)(ii)(G) | Qualifications | “The qualifications of the consultant(s) conducting the Feasibility Study must be included” 1 |
The list is the practical test for a study that an RES applicant files in place of a Resource Assessment. Each of the five analyses has named items, so a reviewer can check the report against the paragraph, and the last two paragraphs ask for the preparer's recommendation and credentials. A study that reaches no recommendation, or that omits who prepared it, leaves two of the seven paragraphs unanswered 1. The technical analysis also overlaps with what a Resource Assessment reports, which is why the rule lets one stand in for the other 1.
The rewrite removed Appendix D and any study threshold.
Rules written before October 16, 2026 describe a program that no longer exists.
91 FR 62600 took effect on 2. For feasibility studies it did four things.
- It removed Appendix D to subpart B, “Contents of Feasibility Study,” and moved the content list into the body of the rule, at 4280.122(a)(8)(ii) in eCFR (the preamble says 4280.131(b)) 21.
- It removed the old study requirement tied to total project cost. We found no project cost threshold that requires a study anywhere in 4280.101 through 4280.199 1. The project cost thresholds that remain apply to other items: a professional engineer's completion certificate under 4280.122(a)(11) and pro forma statements under 4280.131(a)(9)(ii) 1.
- It let an RES applicant choose a Feasibility Study in lieu of a Resource Assessment (4280.131(b)(3)) 1.
- It required that projects be complete and operational before the application is filed, which the preamble gives as a reason for dropping the technical report appendices 2. The codified text says so at 4280.122(a)(1): the project must be for an RES or an EEI "that has been completed between 12 and 24 months prior to the date of application" 1.
Limits in 4280.122(a)(2)(ii) are a maximum request of $500,000 for an RES grant and $250,000 for an EEI grant 1. The rule was published as final with comments open, and the comment period ran to November 2, 2026, so the text may be revised 2.
Dates, amendments and last check.
The eCFR currency date, the rewrite, the close of comments and the last check.
Questions about the REAP grant rule.
Which sections of subpart B name the feasibility study?
Section 4280.104 defines it, 4280.122(a)(8) and 4280.131(b)(3) set the choice between a study and a Resource Assessment, and 4280.125(b)(7) keeps its cost out of the grant 1. The REAP feasibility study page applies the rule to an application.
What does 4280.125 say about a Resource Assessment?
Paragraph (a)(4) allows it as a use of funds unless the cost fell on a different federal award, while paragraph (b)(7) lists “Feasibility studies” as unallowable 1.
What happened to the project-cost trigger for a study?
We found none in sections 4280.101 to 4280.199 as they read on November 5, 2026. The rewrite removed the old Appendix D (contents of a feasibility study) along with the old study rule tied to project cost 21.
Who may conduct the study?
“An independent professional possessing relevant knowledge, expertise, and experience,” under the definition in 4280.104, and the qualifications of the consultant must be included in the report under 4280.122(a)(8)(ii)(G) 1.
Could the rule change again?
Yes. 91 FR 62600 is a final rule with a comment period that ran to November 2, 2026, so USDA may revise it 2. This page was last checked on November 8, 2026.
A renewable energy project? Choose the assessment or the study on its facts.
Feasibility Study Company prepares independent feasibility studies to the content list in 4280.122(a)(8)(ii). Describe the project and we will say whether a study or a Resource Assessment fits it.
Request a methodology briefingPrimary texts and dates.
Texts from the eCFR come first. The eCFR reported itself current as of November 5, 2026, and the stored copy was read against every quotation on November 8, 2026.
- eCFR (Office of the Federal Register), 7 CFR Part 4280 Subpart B, Rural Energy for America Program: Grants for Renewable Energy Systems and Energy Efficiency Improvements, up to date as of November 5, 2026; rewritten effective October 16, 2026.
- Federal Register (USDA), Unleashing American Energy and Economic Prosperity; Rural Energy for America Program (91 FR 62600, FR Doc 2026-20178), final rule with comment period, October 1, 2026, effective October 16, 2026.
- eCFR (Office of the Federal Register), 7 CFR Part 4280 Subpart C, Rural Energy for America Program: Grants for Energy Audits and Renewable Energy Development Assistance, up to date as of November 5, 2026; effective October 16, 2026.