USDA Rural Development · REAP
REAP Feasibility Study Consultant
Feasibility Study Company, an independent REAP feasibility study consultant, prepares the report on economic, market, technical, financial and management feasibility that a Rural Energy for America Program (REAP) renewable energy system applicant may submit in place of a Resource Assessment 1. Under 91 FR 62600, in force from October 16, 2026, the grant rule at 7 CFR 4280.122(a)(8) accepts either document, and the grant cannot pay for a feasibility study 12. Comments closed on November 2, 2026, and the rule may be revised again 2.
REAP now asks for a Resource Assessment or a feasibility study.
The renewable energy system grant rule offers a choice, and the choice is the applicant's.
The Rural Energy for America Program makes grants for two project types: renewable energy systems (RES) and, separately, energy efficiency improvements (EEI). The technical showing differs between them. For an RES project, the rule at 7 CFR 4280.122(a)(8) says RES projects "must demonstrate this information through a Resource Assessment or a Feasibility Study, as described in paragraphs (a)(8)(i) and (ii)" of that section 1. The second route is the one this page covers, and it is the only place in the grant rule where a feasibility study is named as a way to meet a requirement.
The application section says the same thing from the other direction. Section 4280.131(b)(3) tells an RES applicant to provide a Resource Assessment, "or the Applicant can provide a Feasibility Study in lieu of a Resource Assessment" 1. The applicant must also provide the information from whichever document it chooses, so that the Agency can assess the technical sustainability of the project. An EEI project follows a separate track, an Energy Assessment or an Energy Audit, and this page leaves it to the Agency's own forms.
The rule defines a feasibility study at 4280.104 as "a report, conducted by an independent professional possessing relevant knowledge, expertise, and experience, that includes an opinion or finding evaluating the economic, market, technical, financial, and management feasibility of a proposed Project or operation located at a specific site in terms of its expectation for success" 1. Four features of that sentence carry weight in practice. The author is independent. The author is a professional with the relevant knowledge, expertise and experience. The report gives an opinion or finding, which is more than a collection of data. And it is about one site, so a regional or generic study does not qualify, and 4280.222(b)(3) separately excludes state-wide or non-site-specific feasibility studies from renewable energy development assistance 1.
A REAP feasibility study has seven required parts, (A) to (G).
Section 4280.122(a)(8)(ii) lists them. A report that skips a part is incomplete on the rule's own terms.
The same paragraph that defines the study adds that "it must include the following content" 1. Five parts are analyses, one is the author's recommendation and one is the author's qualifications. The table follows the rule's own labels, and the third column says what the study does with each part in practice.
| Part | What the rule lists | What the study does with it | Source |
|---|---|---|---|
| (A) Economic analysis | A cost-benefit analysis covering what the project needs in order to operate, the contracts signed and still to be negotiated, environmental exposure, how the cost compares with the added revenue or benefit, and the wider economic effect, new markets and local development included | Builds the cost and benefit streams from the applicant's own utility bills or sales records, and tests the contracts that the project depends on | 1 |
| (B) Market analysis | Current and future market potential and competition: the type of project, the target market, an analysis of the End User (captive or competitive), any by-product revenue and risk across the industry | Identifies who buys the energy or the by-product, and whether those buyers are captive or can walk away | 1 |
| (C) Technical analysis | Whether the technology will perform and the goods or services can be delivered: commercial availability, track record, service provider experience, infrastructure, labor market, supply of materials, age and dependability of the technology, construction risk | Checks the equipment against the resource at the site and the installer's record, and names the construction risks | 1 |
| (D) Financial analysis | Whether the project can earn enough income, credit and cash flow to carry itself and all of its debt: underwriting, management's assumptions, source of repayment, equity contribution, market demand forecast, peer comparison, short-term credit, raw materials and a sensitivity analysis | Projects cash flow under stated assumptions, and shows how it moves when the energy price or the resource changes | 1 |
| (E) Management analysis | Legal structure, ownership, governance and management: history, professional and educational background, experience, skills and qualifications to implement the project | Describes who will run the system and what they have done before | 1 |
| (F) Recommendation | The recommendation of the independent professional or professionals conducting the study | States a conclusion, including a no-go where the evidence supports one | 1 |
| (G) Qualifications | The qualifications of the consultants conducting the study | Documents who prepared the study and why they are qualified to | 1 |
Two details of the list deserve attention before work starts. The financial analysis includes a sensitivity analysis, and the market analysis includes the End User question, whether the buyer is captive or competitive. Both are the places where an applicant's own forecast is most likely to meet an outside check. A project that sells power to one utility on a fixed contract has a captive End User and a narrow market section, while a project that sells to the open market needs the competition and price work in full.
The grant does not pay for the study, and the Project Cost line now does something else.
Two rules that used to be read together are now separate.
Section 4280.125(b)(7) lists "feasibility studies" among the costs the REAP grant does not pay 1. An applicant that chooses the feasibility study route therefore pays for it outside the grant, either from its own funds or from another source, and does not count it toward the project cost the grant matches. The Resource Assessment is treated differently: 4280.125(a)(4) allows grant funds to pay for a "Resource Assessment, unless the cost was charged in whole or in part to another Federal Award" 1. That cost difference belongs in the choice between the two documents, and the applicant should settle it before asking any author for a quote. The rule also sets the timing: the project must be one "that has been completed between 12 and 24 months prior to the date of application" (4280.122(a)(1)), so the grant application, and any study filed with it, comes after the system is built 1. The preamble gives the reason: "Projects must be complete and operational prior to application filing thus reducing technical risk" 2.
The Project Cost figure of $200,000 still appears in the rule, but it no longer decides whether a study is needed. At 4280.122(a)(11), for larger-scale or more complex projects or those with a Project Cost of $200,000 or more, the Agency requires a completion certificate completed by a professional engineer licensed in the State where the project was completed, as a condition of an award 1. At 4280.131(a)(9)(ii), applicants whose Project Cost is $200,000 or greater must provide two years of pro forma financial statements, including income statements, balance sheets, statements of cash flows and assumptions 1. Those are two other items. A feasibility study may help prepare the pro formas, since its financial analysis in part (D) builds the same cash flow, but the rule does not make one stand in for the other.
This is the point on which older advice on the web is most likely to be wrong. A page that says a REAP application above a given project cost must carry a feasibility study, or that points to Appendix D as the outline, describes the rule before October 16, 2026. The next section dates the change.
What changed on October 16, 2026.
The change is recent, and the comment period it carried may lead to another.
The Federal Register published 91 FR 62600 on October 1, 2026, as a final rule with a comment period, effective October 16, 2026 2. According to the preamble, the notice removed Appendix D to Subpart B and updated 4280.131(b) to reflect in detail the items required in a feasibility study; it also revised the definition of a feasibility study to make clear that the individual conducting the report needs relevant knowledge, expertise and experience and that its findings must concern a proposed project or operation at one specific site 2. In the preamble's section-by-section treatment of conflict of interest at 4280.106, one listed case is that the RES developer conducts the feasibility study, which is a reason to keep the author independent of the equipment vendor 2. Comments were open until November 2, 2026. Because the rule can still be revised, this page carries its check date, and an applicant should read the current text of 4280.122 before it relies on any summary, ours included.
Guaranteed loans use a different section, and the limits are in the rule.
REAP also guarantees loans. The study appears there when the lender or the Agency asks for it.
A REAP guaranteed loan is governed by 7 CFR part 5001, not by part 4280. For RES projects only, 5001.307(d) adds to the application, where the lender or Agency judges it necessary, "an analysis conducted in conformance with the definition of feasibility study found in § 5001.3 and with applicable content in appendix A to subpart D" 3. The wording is permissive, so the study is not a fixed requirement for every loan, and it is also tied to the definition of a feasibility study in 5001.3, which uses the same five areas of feasibility as the grant rule 3. A lender that already asks for a study under its own credit policy can use one report for both purposes if the report meets the contents of both sections.
The dollar limits come from the rule text. Section 5001.406(d) caps the amount of a REAP guaranteed loan at a share of eligible project costs and the total a borrower may hold in REAP guaranteed loans 3. The grant limits are in 4280.122(a)(2)(ii) 1.
Independence and site specificity decide whether a study counts.
Two words in the definition do most of the work.
The definition asks for an independent professional, and the preamble to the October 2026 rule revised it to stress relevant knowledge, expertise and experience 2. The rule text does not define independence beyond that, so the safe reading is the plain one: the author has no stake in selling the equipment, building the system or winning the contract. The preamble's conflict-of-interest discussion points the same way, since it treats the RES developer conducting the study as a conflict case 2. An applicant that takes a study from the installer who will build the system should expect the Agency to ask why.
The second word is site. The definition speaks of a proposed project or operation "located at a specific site" 1, so the study names the parcel, the building or the farm, and its resource and market findings are about that place. A study written for a county, a state or an industry, or one reused from another site with the numbers changed, does not meet the definition. This is also why the REDA provision at 4280.222(b)(3) excludes state-wide or non-site-specific feasibility studies 1.
Part (G) closes the loop. The qualifications of the people who conducted the study must be included 1, which means the application should carry a short statement of each author's background, the sites or projects the author has assessed and any licenses that apply. We prepare that statement as part of the study and do not leave it for the applicant to assemble at the end.
How Feasibility Study Company approaches a REAP study.
This is our practice, not a rule. The rule fixes the contents; the method is ours.
We start from the seven parts, in the rule's order, and build the study so a reviewer can find each part by its letter. The technical analysis starts from the site: the solar resource, the wind record, the feedstock supply or the heat load that the system will use, whichever applies. The economic and financial parts use the applicant's own billing and sales records where they exist, and a stated assumption where they do not. The recommendation states plainly what the evidence supports, because a study that cannot say no has little value to a lender or to the Agency.
We also tell an applicant when a feasibility study is more than the project needs. A small system on a single site, with a well-understood technology and a lender that wants only the resource data, may be served by a Resource Assessment. The rule allows that, and a report is not worth more because it is longer. The feasibility study route fits projects where the market, the contracts or the management plan are open questions, and projects where a lender is already asking for a study.
Application windows, scoring dates and any other date the Agency announces sit in one place, the USDA Rural Development deadline calendar, and this page does not repeat them. Read the calendar first when timing drives the choice, because the study must be complete before the application is filed.
REAP feasibility study questions.
Does a REAP grant application need a feasibility study?
Not under that name alone. For a renewable energy system, technical sustainability can be shown through a Resource Assessment or through a Feasibility Study, whichever the applicant prefers 1. The better fit depends on the project: a feasibility study covers five areas of feasibility for one site, while a Resource Assessment is narrower.
Can the grant pay for the study?
No. The list of unallowable costs in 4280.125(b)(7) includes feasibility studies 1. A Resource Assessment is different: 4280.125(a)(4) makes it an allowable use of grant funds unless another federal award paid for it 1. The applicant carries the study cost, or has a lender or another funder carry it, before filing.
Is there still a project-cost threshold that forces a study?
Not in 4280.122(a)(8), which sets no cost threshold. The $200,000 Project Cost line in 4280.122(a)(11) and 4280.131(a)(9)(ii) now governs other items, a professional engineer's completion certificate and two years of pro forma statements, and not the study 1.
What happened to Appendix D?
The Federal Register notice removed Appendix D to Subpart B and moved its content into the rule text, so the required contents now sit in 4280.122(a)(8)(ii) 12.
Does a REAP guaranteed loan need a feasibility study?
For renewable energy system projects only, the application includes an analysis that follows the feasibility study definition if the lender or the Agency considers one necessary (5001.307(d)) 3. The loan limits are in 5001.406(d).
Where are the REAP deadlines?
Dates sit on a single page, the USDA Rural Development deadline calendar, so that none on this page can go stale. The rule itself may also be revised after the comment period.
Putting a REAP application together? Start with the study's contents.
Send Feasibility Study Company the technology, the site and the funding plan, and it will explain how a REAP feasibility study covers the seven required parts and when a Resource Assessment is enough.
Request a methodology briefingData sources and dates.
Each rule stated here comes from a named, dated source whose text was stored and checked. The REAP rule changed in a final rule effective October 16, 2026, and may change again.
- eCFR (Office of the Federal Register), 7 CFR Part 4280, Subpart B, Rural Energy for America Program Renewable Energy Systems and Energy Efficiency Improvements Guaranteed Loan and Grant Program (sections 4280.104, 4280.122, 4280.125, 4280.131), current to November 5, 2026; amended effective October 16, 2026.
- Federal Register, Unleashing American Energy and Economic Prosperity; Rural Energy for America Program (REAP), 91 FR 62600 (FR Doc. 2026-20178), final rule with comment period, published October 1, 2026; effective October 16, 2026; comments to November 2, 2026.
- eCFR (Office of the Federal Register), 7 CFR Part 5001, Guaranteed Loans (sections 5001.3, 5001.307, 5001.406), current to November 5, 2026.