USDA Rural Development · Requirements

USDA Feasibility Study Requirements

Feasibility Study Company prepares the independent study that USDA Rural Development guaranteed loans call for, and the study answers one question: can this project repay the guaranteed loan, on evidence of its economy, market, technology, finances and management? The USDA feasibility study requirements sit in 7 CFR Part 5001, which asks for a study in three cases. In Business and Industry (B&I), a guarantee above $1,000,000 for a new business needs a study 2, and in Community Facilities (CF) the same holds for a guarantee above $1,000,000 for a new entity or a new activity 3. A third mandatory case, in 5001.140(a)(7), is the startup cooperative borrowing under the B&I stock programs 15. Below those lines the Agency may still ask for one. Ask whether your loan needs a study.

The Definition

What 7 CFR 5001.3 means by a feasibility study.

The regulation defines the document before it says when one is needed.

Section 5001.3 defines the term in a single sentence, in Part 5001 of 7 CFR, which is the OneRD rule for guaranteed loans: a feasibility study "means a report including an opinion or finding conducted by an independent qualified consultant(s) evaluating the economic, market, technical, financial, and management feasibility of the proposed project or operation in terms of its expectation for success as outlined in appendix A to subpart D of this part" 1.

Three parts of that sentence decide how a study is written. It is a report with an opinion or finding, so a spreadsheet or a business plan with a favorable tone does not meet it. It comes from an independent qualified consultant, so the author cannot be the borrower, the sponsor or a party paid by the outcome. And it is measured by expectation for success across five fields. The same section defines financial feasibility on its own as "the ability of a project to achieve sufficient income, credit, and cash flow to financially sustain the project over the long term and meet all debt obligations" 1. That is the test the lender's credit committee applies to the financial section.

Nothing in the definition is a page count or a method. The Agency fixes the scope at the project: the elements of an acceptable study "may vary by project scope" 4. For a guaranteed loan above the threshold, the rule adds that the scope "will be determined by the Agency and is dependent on the complexity of the project and the borrower" 23.

When a Study Is Required

Three mandatory cases, one fixed threshold, one judgment call.

A mandatory study depends on which program is involved, how big the loan is and how new the borrower is.

The rule has two kinds of trigger. The first is mandatory. For a B&I guaranteed loan, 5001.306(a)(3)(i) reads: "For guaranteed loans greater than $1,000,000.00 to a new business, a feasibility study prepared by an independent qualified consultant acceptable to the Agency is required" 2. The Community Facilities rule is parallel: 5001.304(a)(4)(i) requires the same study for a guaranteed loan greater than that amount "to a new entity or an entity conducting a new activity" 3. In both programs the line sits at $1,000,000 23. The third mandatory case turns on the borrower and not on the loan size. For the B&I cooperative stock purchase program, 5001.140(a)(7) says a feasibility study of the cooperative "is required for startup cooperatives", and the Agency may require one for an existing cooperative whose operations the stock-sale proceeds will significantly affect 15.

The second is discretionary. Section 5001.303(c)(4) lets the Agency require an independent study when it "is unable to determine a basis for successful repayment" from the lender's analysis, the borrower's business plan or other project information, or when the project "will have significant impacts on existing operations" 4. The program sections carry the same discretion for loans at or below the threshold: the Agency may ask for a study when the lender's own analysis leaves technical feasibility or economic viability unproven, or if the project would materially change how an existing borrower operates and what its cash flow history shows 23.

ProgramMandatory studyAgency may require a studySection
B&I guaranteedOver $1,000,000, to a new businessLoans at or below that line, or where the lender's file falls short5001.306(a)(3) 2
CF guaranteedOver $1,000,000, to a new entity or new activityLoans at or below that line, or where the lender's file falls short5001.304(a)(4) 3
B&I cooperative stock purchase loansStartup cooperative, whatever the loan sizeExisting cooperatives whose operations the stock-sale proceeds significantly affect5001.140(a)(7) 15
Any OneRD guaranteed loanNone by itselfWhen repayment cannot be established, or existing operations are significantly affected5001.303(c)(4) 4

A smaller B&I request has its own application path. Section 5001.306 sorts applications at $600,000: above it the lender submits the full package, and at or below it the application may follow the shorter path if the Agency finds that the file establishes technical feasibility, market feasibility and economic viability 2. The study threshold and the application split are separate lines, and the business and industry page sets both out.

The practical reading follows from the text. A new business or new entity borrowing over the line, or a startup cooperative taking a stock purchase loan, needs the study before the Agency will act. A borrower under the line, or an established one, should assume the Agency will read the lender's analysis for gaps and ask for a study where it finds them.

Independence

Who may prepare the study, and what the lender writes.

Independence is in the definition; the lender's own evaluation is a separate document with its own section.

For the mandatory studies the preparer is "an independent qualified consultant acceptable to the Agency" 23. For a study the Agency asks for under its general authority, the text says it "should be prepared by a qualified, independent third party" 4. Two tests therefore apply: independence from the project and qualification for the work, and the Agency retains the right to accept or refuse the choice.

The lender has a separate duty. Among the documents a lender must submit, 5001.202(b)(6)(ii) lists "a written evaluation of the feasibility study, business plan, technical report, and engineering and architectural reports, as applicable" 5. The lender reads the study and says what it makes of it. A study that cannot be defended in that evaluation does not help the lender.

The Community Facilities rule draws a distinction that is easy to miss. Its financial feasibility analysis is prepared by "a qualified firm or individual who may be the lender", and the lender's credit evaluation can double as that analysis when it covers the Appendix B items 3. That route is for the cases 5001.304(a) lists, not for a guaranteed loan over the threshold to a new entity, which still needs the independent study under (a)(4)(i) 3. The community facilities page covers the routes in order.

Independence also has a working meaning in the field. A preparer who is paid on closing, who shares an owner with the borrower or who will build or run the facility is not independent in any ordinary sense, and the Agency can refuse the choice. The direct loan rule says so for its own report: the firm or individual must not have "a direct interest in the management or construction of the facility" 12.

The Five Components

Five fields, owned by one note.

This page covers when and who. The components have their own page.

The five components are the economic, market, technical, financial and management fields that the definition lists 1. In a study they work as a chain: the economy supports the market, the market supports the revenue, the technical plan decides what it costs to deliver, the financial section tests whether the result carries the debt, and the management section tests whether this team can do all of it. The Agency can return a study for failing any one of them.

The note on the five USDA components, applied walks each component through a single rural project and shows what satisfies it and what gets returned. Appendices A and B to subpart D of Part 5001, which set out the component content and the financial feasibility reports, are published in eCFR as images 6. We say so plainly: the appendices cannot be searched or quoted from the eCFR text, and this site does not reproduce them. A study is prepared against the appendices themselves, read from the Agency's published document.

The Other Programs

How REAP, VAPG, Community Facilities direct loans and Section 538 differ.

Each program asks for a different document, and only the guaranteed loans use the independent consultant rule.

REAP grants. A final rule at 91 FR 62600, effective October 16, 2026, rewrote the grant rules 9. A renewable energy system applicant now shows technical sustainability "through a Resource Assessment or a Feasibility Study" under 4280.122(a)(8) 7, and under 4280.125(b)(7) the cost of a feasibility study cannot be met from the grant: feasibility studies are not an eligible use of REAP grant funds 8. The study, if the applicant chooses one, is prepared at the applicant's own expense, and it comes after the build: under 4280.122(a)(1) the project is one "that has been completed between 12 and 24 months prior to the date of application" 7. The REAP page sets out the content the rule lists.

Value-Added Producer Grants. An applicant for a working capital grant must provide a feasibility study prepared by a Qualified Consultant under 4284.931(h), with the consultant's name and credentials and the completion date, and the Agency must concur in its acceptability 10. A simplified application, which drops the study, is open for requests under $50,000 and for the other cases 4284.932 lists 11. The VAPG page covers the grant.

Community Facilities direct loans and grants. A direct loan applicant is expected to provide a financial feasibility report by a qualified firm or individual under 1942.17(h)(1), usually folded into the preliminary engineering or architectural report or prepared apart from it by a party with no direct stake in the facility 12. This is a financial report, not the five-component study of the guaranteed rule. The community facilities page covers direct loans, grants and the guaranteed routes together.

Section 538. For guaranteed rural rental housing, 3565.5(a)(4) asks an applicant to "demonstrate market and financial feasibility" 13. A market study requirement exists only as a proposed rule (90 FR 27819) and is not in force 14. The Section 538 page keeps those two facts apart.

Reading the Rule

What the requirement does and does not say.

Three limits on the text are worth stating before a borrower plans a budget.

First, the regulation sets no price, schedule or length for a study, and neither does this page. Second, nothing in 5001.306 or 5001.304 makes the study a guarantee of approval: it is a requirement for a complete application, and the Agency still decides on the whole file. Third, a study written for another lender or another program is not automatically the right document. The OneRD rule names the five fields, the Agency fixes the scope for the project, and the lender must evaluate the result 235.

If you cannot tell which side of the line a loan falls on, begin with three facts the rule uses: the program, the loan amount and whether the borrower counts as a new business or entity. The rest of the USDA section follows from those three.

The same caution applies to the word "new." The rule uses it for a new business under B&I and for a new entity or an entity conducting a new activity under Community Facilities, and it does not define a cutoff in years. A company that has operated for a long time but is starting a different line of business, such as a farm stand becoming a processing plant, raises the question the CF text asks in terms of "a new activity" 3. When the answer is not obvious from the text, the safe course is to ask the Agency's state office early, because a missing study found at the review stage costs the borrower time that the file cannot spare.

USDA Requirement Questions

USDA feasibility study questions.

Is a USDA feasibility study mandatory for every guaranteed loan?

No. Three cases make a study mandatory: a B&I guaranteed loan over $1,000,000 to a new business 2, a CF guaranteed loan over $1,000,000 to a new entity or new activity 3, and a cooperative stock purchase loan to a startup cooperative under 5001.140(a)(7) 15. Elsewhere the Agency may call for one when the file does not let it establish a basis for repayment 4.

Who is allowed to prepare the study?

For the mandatory studies the preparer has to be independent, qualified and acceptable to the Agency 23. When the Agency asks for a study on its own judgment it expects a qualified, independent third party 4. The lender cannot stand in for the preparer on those studies, though it writes its own evaluation of the result 5.

Can the lender's credit memo count as the financial feasibility analysis?

For Community Facilities, in the circumstances the rule lists: a qualified firm or individual, possibly the lender, writes the analysis, and the lender's credit evaluation can serve when it carries the Appendix B items 3. It is a different document from the independent feasibility study required above the threshold.

Do REAP, VAPG and Section 538 follow the same study rule?

No, each has its own text. Since October 16, 2026 a REAP renewable energy system applicant can file a Resource Assessment in place of a Feasibility Study 79. A VAPG working capital grant calls for a study by a Qualified Consultant 10. Section 538 asks the applicant to demonstrate market and financial feasibility 13.

Where are the study components written down?

Appendix A to subpart D of Part 5001 holds the components, and Appendix B holds the financial feasibility reports. The eCFR publishes both as images, so there is no text to quote 6. Our research note walks through the five components on one project.

Find out which USDA study your loan calls for.

Send the program, the loan amount and whether the borrower is new. Feasibility Study Company will say which section applies and what the study has to carry.

Request a methodology briefing
Sources

Data sources and dates.

Rule wording is quoted or closely tracked from the current eCFR and the Federal Register. The five study components appear only as images in eCFR, so none of their wording is reproduced here.

  1. eCFR, 7 CFR 5001.3, Definitions (feasibility study, financial feasibility), current to November 5, 2026; amended December 11, 2025.
  2. eCFR, 7 CFR 5001.306, Business and Industry application requirements, current to November 5, 2026; effective November 29, 2024.
  3. eCFR, 7 CFR 5001.304, Community Facilities application requirements, current to November 5, 2026; effective November 29, 2024.
  4. eCFR, 7 CFR 5001.303, Guaranteed loan application requirements, current to November 5, 2026; effective November 29, 2024.
  5. eCFR, 7 CFR 5001.202, Lender responsibilities, current to November 5, 2026; effective November 29, 2024.
  6. eCFR, 7 CFR Part 5001, Subpart D (Appendices A and B, published as images), current to November 5, 2026.
  7. eCFR, 7 CFR 4280.122, REAP renewable energy system grant requirements, current to November 5, 2026; effective October 16, 2026.
  8. eCFR, 7 CFR 4280.125, REAP ineligible grant costs, current to November 5, 2026; effective October 16, 2026.
  9. Federal Register (Rural Business-Cooperative Service), Unleashing American Energy and Economic Prosperity; Rural Energy for America Program (91 FR 62600, document 2026-20178), October 1, 2026 (effective October 16, 2026).
  10. eCFR, 7 CFR 4284.931, VAPG working capital grant application contents, current to November 5, 2026; effective November 15, 2024.
  11. eCFR, 7 CFR 4284.932, VAPG simplified applications, current to November 5, 2026; effective November 15, 2024.
  12. eCFR, 7 CFR 1942.17, Community Facility loans, application requirements, current to November 5, 2026; effective December 6, 2024.
  13. eCFR, 7 CFR 3565.5, Guaranteed Rural Rental Housing Program (Section 538) eligibility, current to November 5, 2026; effective April 18, 2024.
  14. Federal Register (Rural Housing Service), Multifamily Housing Guaranteed Rural Rental Housing Program Requirements, proposed rule (90 FR 27819, document 2025-10305), June 30, 2025 (proposed, not in force).
  15. eCFR, 7 CFR 5001.140, Cooperative stock/cooperative equity (paragraph (a)(7), B&I cooperative stock purchase program), current to November 5, 2026; amended September 30, 2024.
Inquiries

Request a feasibility study.

Describe the project, the capital source and the timeline, and Feasibility Study Company will reply by email.