Regulatory Library · USDA
USDA Community Facilities Regulations
The USDA Community Facilities regulations are four texts, and each asks for a financial feasibility report: 7 CFR 1942 subpart A for direct loans, 1942.116 for small facilities, 7 CFR 3570 subpart B for grants and 7 CFR 5001.304 for guaranteed loans. Feasibility Study Company prepares the independent reports they call for. This page quotes each section and says which program it governs 1234.
Which text governs depends on the financing.
Direct loans, small facilities, grants and guaranteed loans each have their own section.
| Text | Financing | Operative section | Last amended |
|---|---|---|---|
| 7 CFR 1942 subpart A | Community Facility direct loans | 1942.17(h)(1) 1 | December 6, 2024 1 |
| 7 CFR 1942 subpart C | Fire and rescue and other small facilities | 1942.116 2 | Unchanged since the eCFR history begins (September 2016) 2 |
| 7 CFR 3570 subpart B | Community Facilities grants | 3570.61(d), 3570.65(b)(2) 3 | December 6, 2024 3 |
| 7 CFR 5001 | Community Facilities guaranteed loans | 5001.304 4 | December 11, 2025 4 |
A borrower can meet more than one of these. A grant and loan combination is processed with one application package under 3570.65 3, and the grant section sends the applicant back to the loan sections for its revenue test. A guaranteed loan is a different path, written by a lender under part 5001. For that rule in full, see our part 5001 page, and for the scoping of a study on these projects, our Community Facilities feasibility study page.
Section 1942.17(h)(1) asks every direct loan applicant for a financial feasibility report.
The report is expected from all applicants, and an independent preparer is required in two cases.
Section 1942.17(h)(1), headed “Financial feasibility reports,” begins: “All applicants will be expected to provide a financial feasibility report prepared by a qualified firm or individual” 1. The text says these reports will normally take one of two forms.
- Under (h)(1)(i), the report is “Included as part of the preliminary engineer/architectural report using guides 6 through 10 as applicable” 1.
- Under (h)(1)(ii), it is “Prepared by a qualified firm or individual not having a direct interest in the management or construction of the facility using guide 5” when (A) “The project will significantly affect the applicant's financial operations and is not a utility-type facility but is dependent on revenues from the facility to repay the loan,” or (B) “It is specifically requested by Rural Development” 1.
The second form is the stand-alone report. It is the one an independent feasibility study firm writes, and the independence test is that the preparer has no direct interest in management or construction. In the first form the report travels inside the preliminary engineering or architectural report.
Section 1942.116 sets the revenue test for small community facilities.
The report may be prepared by the applicant on a Rural Development form.
Subpart C of part 1942 covers fire and rescue and other small community facilities projects. Section 1942.116, “Economic feasibility requirements,” says projects must rest on “taxes, assessments, revenues, fees, or other satisfactory sources of revenues” sufficient for operation and maintenance, a reasonable reserve and debt payment 2. It then repeats the rule: “All applicants will be expected to provide a financial feasibility report” 2.
For small facilities the report is either included in the preliminary engineering and architectural report (paragraph (a)) or, under paragraph (b), “Prepared by the applicant using Form RD 1942-54, ‘Applicant's Feasibility Report’” 2. Only this small-facility text names the applicant as the possible preparer; 1942.17(h)(1)(ii) calls for a preparer outside the project's management or construction.
Sections 3570.61 and 3570.65 tie grants to the same report.
The grant is sized to what feasibility needs, and the report is part of the application.
Section 3570.61(d), “Economic feasibility,” provides: “All projects financed under the provisions of this section must be based on satisfactory sources of revenues as outlined in 7 CFR 1942.17(h) and 1942.116. The amount of CFG assistance must be the minimum amount sufficient for feasibility which will provide for facility operation and maintenance, reasonable reserves, and debt repayment” 3. The report therefore also supports the size of the grant request: it shows what the facility needs to be feasible, and the grant may not exceed it.
Section 3570.65(b)(2) lists “Financial feasibility report” among the forms the applicant submits for a complete application once notified that it is eligible for funding 3.
Section 5001.304 sets three tiers of report for a guaranteed loan.
The rule assigns the tier by loan size, borrower and history, so the lender does not pick.
For guaranteed loans the rule says “a lender seeking a loan guarantee for a CF project must submit a financial feasibility report prepared by a qualified firm or individual acceptable to the Agency” (5001.304) 4. Paragraph (a) allows a financial feasibility analysis, which “will be prepared by a qualified firm or individual who may be the lender,” for guaranteed loans of $25 million or less to existing community facilities, for loans backed by a general obligation bond or other tax support, and for borrowers whose audited statements show the ability to pay existing and new debt service 4.
Paragraph (a)(4) lets the Agency require a feasibility study, and (a)(4)(i) makes one mandatory: “For guaranteed loans greater than” $1,000,000 “to a new entity or an entity conducting a new activity, a feasibility study prepared by an independent qualified consultant acceptable to the Agency is required” 4. Paragraph (b) adds that where the analysis route does not apply, the examination-opinion study is required, and it must be “prepared in accordance with the standards of attestation of the American Institute of Certified Public Accountants,” by a preparer carrying professional liability insurance 4. The section also limits the occupancy that projections for assisted living and skilled nursing facilities may assume to 90 percent, so a study for one of those projects has to run its numbers at or below that level 4.
Dates, amendments and last check.
The eCFR date, the amendment dates of each text and the last check.
| Item | Date |
|---|---|
| eCFR up to date as of | |
| 1942 subpart A, last amended | (the last substantive change to 1942.17 was in June 2022) 1 |
| 3570 subpart B, last amended | December 6, 2024 (sections 3570.61 and 3570.65 unchanged since December 2016) 3 |
| 5001.304, in force since | 4 |
| Last checked by Feasibility Study Company | November 8, 2026 |
Questions about the Community Facilities rules.
What does 1942.17(h)(1) expect of a direct loan applicant?
A financial feasibility report: “All applicants will be expected to provide a financial feasibility report prepared by a qualified firm or individual” 1.
When must the report come from a firm with no interest in the project?
When the report is prepared on Guide 5 rather than inside the preliminary engineering report, it must come from a firm or individual “not having a direct interest in the management or construction of the facility” if the project will significantly affect the applicant's finances and depends on facility revenues to repay, or if Rural Development specifically requests it (1942.17(h)(1)(ii)) 1.
What do 3570.61(d) and 3570.65(b)(2) say about grants?
Section 3570.65(b)(2) lists a “Financial feasibility report” among the forms for a complete application, and 3570.61(d) ties the grant to revenue sources as outlined in 1942.17(h) and 1942.116 3.
What does 5001.304(a)(4)(i) add for a guaranteed loan?
A mandatory study by an independent qualified consultant when the loan is above $1,000,000 and the borrower is a new entity or is conducting a new activity 4. The Agency can ask for one in other cases too 4.
What does 5001.304(a) say about the lender's credit evaluation?
It can double as the analysis: “The lender's credit evaluation may serve as the financial feasibility analysis provided it includes the items outlined in appendix B to subpart D” 4.
A community facility needs a report the Agency and the lender will both read.
Feasibility Study Company works with community facility sponsors, from direct loan applicants to guaranteed loan borrowers. Tell us the financing and we will confirm which of the four texts governs it.
Request a methodology briefingPrimary texts and dates.
Four eCFR texts are quoted. The eCFR gave November 5, 2026 as its currency date, and each quotation was matched to a stored copy on November 8, 2026.
- eCFR (Office of the Federal Register), 7 CFR Part 1942 Subpart A, Community Facility Loans (section 1942.17), up to date as of November 5, 2026; last amended December 6, 2024.
- eCFR (Office of the Federal Register), 7 CFR Part 1942 Subpart C, Fire and Rescue and Other Small Community Facilities Projects (section 1942.116), up to date as of November 5, 2026; section unchanged since the eCFR history begins (September 2016).
- eCFR (Office of the Federal Register), 7 CFR Part 3570 Subpart B, Community Facilities Grant Program, up to date as of November 5, 2026; last amended December 6, 2024.
- eCFR (Office of the Federal Register), 7 CFR Part 5001, Guaranteed Loans (section 5001.304, community facilities), up to date as of November 5, 2026; last amended December 11, 2025.