Gas Station and C-Store · EV Charging

EV Charging and Alternative Fuel Feasibility Studies

A lender looking at fast chargers on a fuel or convenience site needs revenue per port built from observed utilization and price, the grant award and its conditions in writing, and the utility's commitment to serve the load. The market evidence is thin but dated: U.S. fast-charging ports ran at 15.6% utilization in the first quarter of 2026 at $0.53 per kWh 2, against a modeled corridor breakeven of $0.42 per kWh 1. The research found no SBA, USDA or bank underwriting rule written for chargers, so the study carries the whole case.

15.6%
U.S. DC fast-charging utilization, first quarter 2026, down from 16.2% 2
$0.53
Average DC fast-charging price per kWh, first quarter 2026 2
$0.42
Modeled corridor breakeven price per kWh, 20-year average 1
76,236
Public DC fast-charging ports in the U.S., September 1, 2026 4
How It Earns

A charger earns on kilowatt-hours sold, and most hours it sells none.

The observed market price sits above the modeled breakeven. Utilization decides whether the gap reaches the bottom line.

This page covers public DC fast charging at fuel stations, convenience stores and travel centers, which is where the research found almost all of its evidence. Other alternative fuels (compressed and liquefied natural gas, propane, E85 and hydrogen) appear in the federal station counts by state, updated October 6, 2026 20, but the research extracted no figures for them, and a study for one of those fuels would start from that state table and the fuel supplier's contract.

A fast charger earns money when a car is plugged in. Its revenue is sessions multiplied by energy per session multiplied by price, less the electricity bill, demand charges, network fees and maintenance. Two dated sources bracket the economics. Peer-reviewed work by NREL authors modeled a corridor fast-charging breakeven price of $0.42 per kWh as a 20-year average 1. Paren's market data for the first quarter of 2026 show an average price of $0.53 per kWh, stable on the year, with 200 to 220 sessions per port a month and utilization of 15.6%, down from 16.2% a year earlier 2.

The two figures are on different bases: one is a modeled lifetime average for a corridor station, the other an observed national average price in one quarter. Read together, they say that the going price clears the modeled breakeven, and that the margin depends on keeping utilization where the market already is. A station at half the national utilization does not earn half the profit; with fixed demand charges and network fees, it may earn none. The research found no published revenue per port and no energy per session, so a study cannot multiply its way to revenue from national figures. It has to use session and energy data from comparable stations near the subject.

Revenue driverFigurePeriodSource
DC fast-charging utilization15.6% (16.2% a year earlier)First quarter 20262
Sessions per port per month200 to 220First quarter 20262
Average price$0.53 per kWh, stableFirst quarter 20262
Modeled corridor breakeven price$0.42 per kWh, 20-year average2025 study1
EVs as a share of light-duty vehicles: Yesway's nine states; elsewhere1.2%; 2.4%2024 (EIA data)7

Local demand varies more than the national averages suggest. Yesway's securities filing, citing EIA data, put electric vehicles at 1.2% of registered light-duty vehicles in its nine mostly rural Southwest and Midwest states in 2024, half the 2.4% share elsewhere 7. The research found no site-level demand metric for charging. A study should therefore pull registrations for the subject's county, the corridor's traffic count and the nearest competing fast chargers, and set utilization below the national figure where registrations are below the national share.

Supply

Fast-charging supply is growing quickly, and the counts depend on who is counting.

Two series track U.S. fast-charging ports. They use different methods, and a study must not mix them.

SeriesPublic DC fast-charging portsDateSource
Federal station locator (AFDC)67,916, including 951 ports temporarily unavailableJanuary 1, 20263
Federal station locator (AFDC)76,236September 1, 20264
Federal station locator (AFDC), via a third party77,320 fast ports of 260,188 public ports at 82,530 locationsSeptember 30, 20265
Paren private count73,394 ports at 13,708 locationsEnd of first quarter 20262
Paren private count80,964 ports at 14,614 locationsEnd of third quarter 20266

Within the federal series, public fast-charging ports rose from 67,916 on January 1, 2026 to 76,236 on September 1 34. Paren's own count added 3,387 ports in the first quarter of 2026, up 1.7% on the year; another reading of the same report gives 3,400 2. New stations are getting larger, averaging 5.5 ports in that quarter against 4.6 a year earlier 2. For a site host, that trend matters twice: a competitor arriving with six or eight ports changes the local supply more than a two-port site did, and a four-port subject may look small against it.

The lesson for a lender is to read every port count with its series and date. A study that pairs a federal January figure with a private September figure invents growth, and one that compares a station-level count from one series with a location count from the other confuses ports with sites. We cite one series per comparison and say which it is.

What It Costs

Cost per port climbs with power, and the utility bill is the open question.

The research's dated cost evidence comes from one peer-reviewed study. Utility interconnection, often the largest unknown, is not priced anywhere in it.

Charger powerEquipment per portInstallation per portPeriodSource
150 kW$84,300$69,9002025 study1
250 kW$113,100$80,3502025 study1
350 kW$141,900$90,8002025 study1

The NREL authors' figures show equipment cost rising from $84,300 per port at 150 kW to $141,900 at 350 kW, and installation from $69,900 to $90,800 1. A site host choosing power is choosing between a lower capital cost and the ability to serve newer vehicles faster, which affects how many sessions a port can deliver in a busy hour. The study should state the charger model and power, the number of ports and the vendor's quote, and should show those against the published per-port figures.

What the research could not price is the electrical service. It found no published utility load, transformer or interconnection cost for fuel-site chargers, and no demand-charge benchmark across utilities. It does hold one municipal demand tariff, which shows the structure a lender should ask about. The City of Lockhart, Texas, which sells its own electricity, bills general service demand customers a fixed $33.42 a month, $0.03773 per kWh on the first 20,000 kWh and $5.75 per kW of demand above 40 kW, and adds its purchased power cost to every kWh 24. Under a charge like that, the bill follows the station's peak draw as well as the kWh it sells, so a slow month with a few full-power sessions can still carry a large demand line. Energy prices also differ by state: EIA data compiled by the University of Wisconsin put industrial power at 8.54 cents per kWh in Wisconsin in 2024, against 6.80 cents in Iowa 25. Those are industrial averages, not the commercial tariff a fuel site pays, so they set scale only. Service, interconnection and demand costs depend on the utility, the existing service at the site and the tariff the station will pay, and on some sites they decide the project. A lender should require the utility's written service commitment, the interconnection cost estimate and the applicable commercial tariff before relying on any revenue line.

Grants

NEVI money is real, but it stopped once and its terms are set state by state.

Most fast chargers at fuel sites are being built with federal formula funds passed through state programs. The program's history is part of the credit risk.

The National Electric Vehicle Infrastructure program carries $5 billion through FY2026, of which $4.2 billion had been made available since FY2022, and $885 million was apportioned for FY2026 8. Its history is uneven. By February 6, 2025, $527 million had been obligated, and on February 10, 57 NEVI stations were open in 15 states 9. That day, FHWA paused the program; revised interim final guidance followed on August 11, 2025 8, states resubmitted their deployment plans under it 13, FY2026 funds became available in October 2025, and a court entered final judgment in January 2026 8. The Consolidated Appropriations Act, 2026 moved some unobligated NEVI funds elsewhere, and the separate Charging and Fueling Infrastructure program remained paused when CRS reported 8. By late 2025, at least 384 ports paid for by NEVI had been built 10.

The guidance sets the station a grant will pay for: at least four network-connected DC fast ports, each able to deliver up to 150 kW at the same time, available around the clock 12, with a federal share of 80% 11. State awards show what that buys at fuel sites. Maryland's first NEVI station opened on November 12, 2025 at a Pilot/Flying J on I-95 in Elkton, with 8 ports and a $450,000 Round 1 award 16; a Pilot travel center on I-68 in Grantsville opened on October 21, 2025 with 4 ports and $475,000 17. Maryland's third round, announced August 18, 2026, made five conditional awards for 24 fast-charging ports at gas stations and convenience stores, a hotel and a commercial plaza, with approximately $3.7 million of federal money against about $918,000 of private funds, and the stations are expected to open by late 2028 14. Illinois has made $67.2 million of conditional awards over three rounds for 91 stations with 489 ports 15. Its first station built under the program, a Phillips 66 fuel stop at Casey near I-70, cut its ribbon on July 22, 2026 with four DC fast ports and a NEVI grant of $854,641 15. The three opened stations named here share a pattern: four to eight ports added to an operating fuel stop, so the store, not the chargers, carries the site.

Large operators are building on the same funds. Love's 2026 plan includes 100 NEVI EV stalls 18, and in Hillsborough County, Florida, a project for six electric truck charging stations at an I-4 facility would use $24.7 million of NEVI funds, with construction expected in 2027 after a board vote on October 14, 2026 19. Pilot, building with General Motors, reported EV charging at about 245 locations in fiscal 2025, under a plan for up to 2,000 stalls at up to 500 sites 23. A network of that size can carry slow chargers at quiet exits while the busy ones pay; a single-site host cannot. For a single-site borrower, the grant is a third source of funds in the sources and uses. The study should show the award letter, the match the host must fund, the date the money is paid and the operating commitments that come with it, and the coverage test should still pass if the award is delayed.

How Lenders Underwrite It

No lender rule covers chargers, so the study has to.

The research found no SBA, USDA or bank underwriting rule specific to EV charging. The loan is underwritten on the whole site.

Chargers on a fuel site sit on property SBA lists as a gas station, a special purpose property 21, so the 504 contribution follows the site: 15%, or 20% for a new business 21. A new site under 7(a) must reach 1.15x coverage within two years 21. Beyond those site rules, the research found no SBA, USDA or bank guidance on charging equipment, no named lender to charging projects and no performance data. Nothing in the rules makes a study compulsory, for chargers or anything else: 13 CFR 120.160(b): SBA may require professional appraisals, a survey, or a feasibility study 22. For the program side, see SBA 7(a) and 504 financing.

In practice, a lender financing a site with chargers asks the study to do three things. Show the store and fuel business carrying debt service with the chargers at low utilization, so the loan does not depend on the newest revenue line. Put the grant in the sources and uses with its payment timing and its clawback or operating conditions. And document the electrical service, because a charger that cannot draw its rated power cannot earn its projected revenue. Where those three are missing, the chargers should be presented as an option the borrower funds after the core loan closes, not as part of the base case.

Where It Fails Review

Where charging projects stall in review.

Each of these failures is visible in the evidence the research found, or in what it could not find.

  1. Utilization is assumed, not evidenced

    National utilization fell from 16.2% to 15.6% over the year to the first quarter of 2026 2. A pro forma that projects rising utilization at a rural site, where registrations may be half the national share 7, needs local evidence for it.

  2. The grant is treated as certain

    NEVI obligations stopped on February 6, 2025 and restarted only after new guidance in August and a court judgment in January 2026 8. Maryland's latest awards are not expected to open until late 2028 14. A file that needs the grant to close, and does not say when it pays, carries program risk the lender has not priced.

  3. The station does not meet the program minimum

    A grant-funded station needs at least four ports, each able to deliver up to 150 kW at once, around the clock 12. A design below that, or a state plan with stricter terms, puts the award at risk.

  4. The electrical service is unpriced

    The research found no published utility load or interconnection cost for fuel-site chargers. Projects that reach the lender without a utility commitment and cost estimate are not ready for credit.

  5. Port counts are mixed across series

    Federal and private counts differ by method 46. A competitor analysis that blends them misstates supply growth and the subject's share of it.

Worked Cases

No case on this site makes chargers the subject.

Chargers appear in our cases as competitors and as part of the travel-center field, not as the project being financed.

None of our gas station cases makes EV charging its subject, and none models charger revenue. The closest evidence sits in the competitor censuses. In the Versailles, Ohio case, a stand-alone electric charging listing appears at the campus address of Midmark, the village's anchor employer, alongside three fuel-and-convenience operators; it shows how a charger can enter a small market without a fuel station attached. In the Lockhart, Texas case, the pipeline list includes a planned Buc-ee's at Boerne approved with EV chargers, outside the subject's next ring. And near the Cartersville, Georgia case, an EV battery plant is a demand driver for the exit, a reminder that EV-related industry and EV charging demand are different things.

Our gas station and c-store hub treats charging as an add-on to the fuel formats, and at a fuel site it rarely stands alone. Branded operators are adding grant-funded chargers to existing stations, as the Phillips 66 example on the branded fuel page shows. Interstate megasites now open with chargers in the plan, which the interstate and highway page covers alongside their fueling positions. For a lender, the useful comparison is that chargers add a revenue line with less evidence behind it than either fuel or the store, which is why we underwrite them last.

EV Charging Questions

EV charging station feasibility questions.

How does a study estimate revenue for a fast charger?

From sessions, energy per session and price at comparable stations. National data show 200 to 220 sessions per port a month and an average price of $0.53 per kWh in the first quarter of 2026 2. The research found no published revenue per port or energy per session, so the study must take those from the charging network's own data for nearby sites or from the operator's records.

What does a fast-charging port cost?

It rises with power. Peer-reviewed NREL work puts equipment at $84,300 per port at 150 kW, $113,100 at 250 kW and $141,900 at 350 kW, with installation of $69,900, $80,350 and $90,800 respectively 1. Utility service upgrades can add more, and the research found no published utility load or interconnection cost for fuel-site chargers.

What does a NEVI-funded station have to provide?

At least four network-connected DC fast ports, each able to deliver up to 150 kW at the same time, open around the clock, under FHWA's August 11, 2025 interim final guidance as summarized by a charging company 12. The federal share is 80% 11. A study should check the subject's design against the state's current plan, since states resubmitted their plans after that guidance 13.

Can NEVI grant money count toward the borrower's equity?

The research found no SBA or USDA rule on that point. A grant is a third source in the sources and uses, not the borrower's injection, and its timing matters: if it reimburses costs after construction, the project needs bridge funds. We treat the award letter and its payment terms as a lender condition.

Is EV demand strong enough near my site?

It varies sharply by region. Yesway's filing, using EIA data, put electric vehicles at 1.2% of registered light-duty vehicles in its nine states in 2024 against 2.4% elsewhere 7. The research found no site-level demand measure, so we use state registration data and the corridor's traffic, and we show utilization below the national average as the base case where registrations are low.

Does a lender treat chargers as part of the gas station?

On a fuel site, the chargers sit on property SBA lists as a gas station, a special purpose property 21. The research found no rule that treats the charging equipment differently, so the lender will look at the whole site's coverage. A study should show the store and fuel business carrying the debt service with the chargers at low utilization.

Adding fast chargers to a fuel site? Start with utilization and the grant terms.

We study chargers at fuel stations, convenience stores and travel centers as part of the whole site's credit. Ask for a methodology briefing to see how revenue per port is built, where a grant sits in the sources and uses, and which conditions a lender will set.

Request a methodology briefing
Sources

Data sources and dates.

Every figure on this page traces to a named, dated source. Port counts come from two series with different methods (the federal station locator and the private Paren count) and are never combined; secondary sources are marked.

  1. NREL authors, in a peer-reviewed journal (ScienceDirect), Economics of electric vehicle corridor fast charging in the United States, 2025.
  2. EVChargingStations.com, reporting Paren data (secondary), Paren's Q1 2026 Report, April 23, 2026 (first quarter 2026).
  3. EVChargingStations.com, citing DOE Alternative Fuels Data Center (secondary), Largest DC Fast-Charging Networks in the US: January 2026, January 2026 (count as of January 1, 2026).
  4. EVChargingStations.com, citing DOE Alternative Fuels Data Center (secondary), Largest DC Fast-Charging Networks in the US: September 2026, September 2026 (count as of September 1, 2026).
  5. EngiMarket, citing DOE Alternative Fuels Data Center (secondary), EV Charging Stations by State, data as of September 30, 2026.
  6. Paren, US EV Fast Charging, Q3 2026, end of the third quarter of 2026.
  7. Yesway, Inc., Form S-1 Registration Statement, March 27, 2026 (2024 EIA registration data).
  8. Congressional Research Service, Implementation of Electric Vehicle Charging Infrastructure Programs: CFI and NEVI (R48996), 2026.
  9. Congressional Research Service, Status of Federal Implementation of EV Charging Infrastructure (IN12556), February 2025 (data as of February 6 and 10, 2025).
  10. ACT News (secondary), The United States of NEVI, late 2025.
  11. Federal Highway Administration, NEVI Formula Program Interim Final Guidance, August 11, 2025.
  12. Electric Era, summarizing the FHWA interim final guidance (secondary), NEVI is back: navigating new rules and retailer opportunities, 2025 (guidance of August 11, 2025).
  13. Electrification Coalition (secondary), National Electric Vehicle Infrastructure (NEVI) Program Updated Guidance, August 2025.
  14. Maryland Department of Transportation, Five New Fast-Charging Projects, August 18, 2026.
  15. Illinois Department of Transportation, Casey's next big thing: Illinois' first electric vehicle charging station built through federal program now up and running, July 2026.
  16. Maryland Department of Transportation, Maryland Celebrates Opening of First NEVI-Funded EV Chargers, December 11, 2025 (opened November 12, 2025).
  17. Maryland Department of Transportation, NEVI Round 1 Awards Site List and Status, June 2026 (opened October 21, 2025).
  18. Love's Travel Stops, Love's to focus on growth and reinvestment in 2026, February 5, 2026.
  19. Plan Hillsborough, Electric Truck Charging Project Planned for I-4 Facility, October 2026 (board vote October 14, 2026).
  20. U.S. Department of Energy, Alternative Fuels Data Center, Alternative Fueling Station Counts by State, updated October 6, 2026.
  21. U.S. Small Business Administration, SOP 50 10 8.1, Lender and Development Company Loan Programs, with Technical Policy Updates, effective October 1, 2026.
  22. eCFR, 13 CFR 120.160, Loan conditions, current to October 7, 2026.
  23. Berkshire Hathaway Inc. (SEC filing), Form 10-K, fiscal year 2025 (Pilot EV charging sites and the GM plan), 2026 (fiscal 2025 data).
  24. City of Lockhart, Texas, Services Rates (electric rates, General Service Demand), rates as posted, checked October 16, 2026 (the page states no effective date).
  25. University of Wisconsin-Madison, Center for Research on the Wisconsin Economy (CROWE), citing U.S. EIA (secondary), Winning the AI Race: Who Should Pay for Wisconsin's Data Center Boom?, August 4, 2026 (2024 industrial electricity prices).